Project case study

Rock Armour Delivery – Elmer

Coastal Defence Framework 1 (CDF1) — Environment Agency

7,259t

Total tonnage delivered

3

Deliveries to beach

55 hrs

Discharge & up-anchor (vs 72-hour allocation)

0

Demurrage / additional costs
Dji 0155

Scope

GRS delivered 7,259t of rock armour to Elmer beach as part of the CDF1 coastal defence works: 5,058t of 6–10t armourstone and 2,201t of 60–300kg armourstone, discharged across three separate deliveries. <em>The aggregate was sourced from Larvik, Norway — a secondary product with zero carbon production cost.</em>

Challenge

The operation required loading and discharging within a 24-hour window per delivery. Armourstone was loaded via transhipment 3.0nm offshore before the barge grounded on the beach for a 12-hour tidal window at each landing. The landing zone sat between two groynes with only a 50m gap, and a 1.2kt east-to-west tidal flow had to be actively countered — requiring a two-tug operation throughout each discharge.
Dji 0155
Dji 0155

Execution

A two-tug spread held station against the cross-flow while the barge was worked in and grounded within the narrow groyne gap. Discharge and up-anchor was completed in 55 hours against a 72-hour allocation across the operation.

Result

All 7,259t delivered on budget, with no demurrage or additional costs incurred. The project was completed for Volker Stevin under the CDF1 framework, with the Environment Agency as end client.

Client

Volker Stevin

End client

Environment Agency

Framework

Coastal Defence Framework 1 (CDF1)